Thursday, July 28, 2011

Internet was Down-Catching Up


Preparing to pour concrete that will form the second floor:

Five and a half hours later, hauling cement up to the roof, bucket by bucket...the job is done:

Because of weight considerations, one of the walls had to be constructed out of foam:

This is how supplies are lifted to the second story:

Second story is progressing:


Downstairs Interior arches and roof:

Upstairs foam wall is nearly complete, covered with 2 inches of concrete each side:

Looking toward the master bedroom from master bath: